Sign contracts of some packages for Thai Binh 2 Project

On 9 November 2015, in Hanoi, PVC and subcontractors signed contracts of some packages for Thai Binh 2 Thermal Power Plant Project, consisting of: "Air-conditioning and ventilation system for turbine building and central control building" package with Hoa Hong-Hung Tri consortium; "Providing valves, steel pipes and auxiliaries for cooling water intake and discharge system" package with Hoang Duong - Hoa Nguyen consortium. The total value of packages is about 90 billion dongs.


Currently the project is in process of installation of steel structures, procurement and delivery of materials and equipment. PVC also continue signing packages with subcontractors to complete other work items.

Through a process of strict analysis and evaluation for subcontractor's capability and experiences, PVC has selected the above-mentioned subcontractors. Speaking at the signing ceremony, Mr. Nguyen Huy Hoa, Member of PVC BOD, affirmed that PVC will create the most favourable conditions for subcontractors to proceed the work, at the same time, subcontractors are required to implement the packages with assurance of schedule and quality.

Subcontractors also commited to implement and complete the packages with their best as required by the employer.

Viet Duy


buca escort