PVC and PVC-PT/MIE/Viettronics signs contract for the slag removing system of Thai Binh 2 Thermal Power Plant

On 1 June 2015, in Hanoi, PVC and the consortium of PVC-PT/MIE/Viettronics signs the contract of engineering, supplying materials and equipment, installing and commissioning the slag removing system of Thai Binh 2 Thermal Power Plant with the package price of more than 151 billion dongs.

The slag removing system
is one of the important items of the Project. After evaluating capability and experiences of subcontractors, PVC has selected the consortium of PVC-PT/MIE/Viettronics as a partner for engineering, supplying materials and equipment, installing and commissioning this package of slag removing system. The package is scheduled to be completed in 17 months from the commencement date. 
Viet Duy 